Migration Timeline
The upgrade to the 1NCE Platform 2.0 is a mandatory platform upgrade and runs in phases through the end of 2026. Use this page to understand when each milestone happens.

Upgrade phases
| When | Milestone |
|---|---|
| August 2026 | 1NCE Inc. accounts: continuous upgrades to the 1NCE Platform 2.0 begin. You will be informed via email once your account has been upgraded. |
| October 1, 2026 | 1NCE Inc. accounts: new SIM card orders ship on the 1NCE Platform 2.0 core network. Existing SIM cards are not affected. |
| Q4 2026 | All other tenants: continuous upgrades begin, and new SIM card orders ship on the 1NCE Platform 2.0 core network. You will be informed via email once your account has been upgraded. |
| End of 2026 | All customers: Management API v1 retired — the switch to API v2 must be finalized. Hard cutoff for new activations on the 1NCE Platform 1.0. |
Tenant-specific timelines
The August schedule applies to 1NCE Inc. accounts. 1NCE GmbH and APAC tenants follow in Q4 2026 — you will be informed via email ahead of your upgrade.
Cutoff dates to plan around

Management API v1 retires at the end of 2026
If you use the Management API, plan your upgrade to API v2 well before the cutoff. See Management API Migration.
1NCE Platform 1.0 new-activation cutoff
From the end of 2026, new activations on the 1NCE Platform 1.0 are no longer possible. New orders ship on the 1NCE Platform 2.0 core network from October 1, 2026 for 1NCE Inc. accounts, and starting Q4 2026 for all other tenants.